What term is used for the amount of time an activity can be delayed?
Total Float
Total Float (TF)
The amount of time that an activity can be delayed from its early start without delaying the project finish date.
Is the amount of time an activity can be delayed and not delay the project?
Total Float (TF)
It is the amount of time by which an activity can be delayed without delaying the project duration.
Is the amount of time an activity may be delayed from its early start without delaying the planned project finish date?
ITPM-06-Time_Management_Vocabulary
A | B |
---|---|
total slack (total float) | The amount of time an activity may be delayed from its early start without delaying the planned project finish date |
Tracking Gantt chart | A Gantt chart that compares planned and actual project schedule information |
What is the amount of time an activity may be delayed without delaying a succeeding?
A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.
What would be an example of lag time between two activities?
Example of Lag
For example, the duration of the first activity is three days and two days for the second activity. After completing the first activity, you wait for one day, and then you start the second. Here, we say that the lag time is one day.
What is the amount of time that a schedule activity can be delayed without delaying the early start of any successor activity or violating a schedule constraint?
Total Float is the amount of time a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. The Total Float (also referred to as just float or slack) of any activity on the Critical Path is usually 0 (zero).
What indicates the amount of time by which an activity?
Total float: It is the amount of time that the completion time of an activity can be delayed without affecting project completion time.
What is slack time in CPM of activity, network?
It denotes the amount of time each activity can be delayed without violating the entire project duration. The slack of an activity can be calculated as the difference between its latest start and earliest start time, or alternatively, as the difference between its latest and earliest finishing time.
What is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date quizlet?
The term total slack refers to the amount of time an activity can be delayed without delaying the start of a subsequent activity. 6.
What is the measure that determines the flexibility of an activity to be delayed or extended from its early start date without delaying the project finish date?
Total Float
Total Float is the amount of time by which you can delay an activity from its early start date without delaying the project finish date.
What term describes a necessary delay before a successor activity can begin?
Lag. the amount of time a successor’s start or finish is delayed from the predecessor’s start or finish. In a finish-to-start example, activity A must finish before activity B can start.
What is the minimum amount of time a dependent activity must be delayed to begin or end?
Lag
1) The correct answer is option c) Lag. In project scheduling, Lag or Lag Time is the time that is required to delay to begin or end an activity…
What is crashing of time cost in construction?
Project crashing is the name given to schedule compression techniques that are used when a person wants to shorten the duration of a project without changing the scope. … The project crashing results in a high direct cost to the project, but also gives clear identification for optimal time cost.
What do we mean by an activity’s late finish date quizlet?
Late Finish. The latest an activity can finish without affecting the project duration.
Which of the following activities is not considered a project?
Ans. (b ) Producing automobile tires is not considered as a project.
What activities must be completed immediately before a particular activity?
Activities that must be completed immediately before an activity are called predecessor activities.
Why are activities on the critical path critical?
Critical path activities are the project tasks that must start and finish on time to ensure that the project ends on schedule. A delay in any critical path activity will delay completion of the project, unless the project plan can be adjusted so that successor tasks finish more quickly than planned.
Which of the following is not considered to be characteristics of project?
(D) Only for internal use is not considered to be a characteristic of a project.
What is project life cycle?
What is the project life cycle? The project life cycle includes the steps required for project managers to successfully manage a project from start to finish. There are 5 phases to the project life cycle (also called the 5 process groups)—initiating, planning, executing, monitoring/controlling, and closing.
Which of the following is not part of the definition of a project?
The correct answer is A. Repetitive activities. A project is a once of endeavour rather than happening on a repetitive way since it has a defined…